Hi all, I was wondering if anyone can sahre their current process to isolate pole mounted capacitor banks. We are reviewing our HV Switching Procedure and wondering if our current process is over the top. Currently, de-energise the capacitor bank via a downstream switch, earth to discharge, open and remove the isolators and bridge out the bushings.